W.P.1: Proje Yönetimi
09.01.2025

 

W.P.1. Project Management

Work Package Leader

Participating Organisations

Activities

ATRH

-

W.P.1. Project management preparation and plan development

ATRH

All Partners

W.P.2. Communication strategy & plan

ATRH

All Partners

W.P.3. Internal progress reports & payments

ATRH

All Partners

W.P.4. Technical & financial reports

ATRH

All Partners

Workpackage aim

The project management work package will contribute to monitoring the progress, quality, and success of project activities. By the quality strategy, the coordinator institution will monitor the quality strategy to ensure that the project progresses according to the determined timetable and in achieving the targetsThe project management work package will facilitate the monitoring of project activities in terms of progress, quality, and success. In accordance with the quality strategy, the coordinating institution will oversee the implementation of the quality strategy, thereby ensuring that the project progresses in accordance with the predetermined schedule and achieves the established targets.

Project monitoring activities

1. Integration of collaborative methodology and partnership

2.Implementation of activities according to work packages

3. Progress of activities according to timetable and compliance with deadlines

4.Verifying and reporting/sharing results and observations, and

5. Level of dissemination effort and sustainability of results.

Quality and success indicators

The activities included in the project management work package will facilitate the monitoring of project progress, quality, and success. The coordinating institution will oversee the implementation of the quality strategy, ensuring that the project progresses in accordance with the established timeline and achieves the desired outcomes. It is anticipated that the partners will adhere to the Erasmus+ budgetary guidelines, align with the project roadmap, comply with the project management process, and align with the quality indicators set forth for the work packages. Furthermore, it is expected that the partners will submit project reports in a timely and comprehensive manner. During the Online TPM in Turkey, the timetable will be reviewed with the partners, and any necessary updates will be made. In addition, quality and success indicators are: 12 quality indicators, including key performance indicators (KPIs):

KP1 - Feedback and Surveys,

KP2 - Stakeholder Engagement Survey,

KP3 - Number of websites and social media usage,

KP4 - Training Activity Success Rate (pre-test-post-test),

KP5 - Level of Participation in Regular Monitoring Meetings, and

KP6 - Realisation Level of Activities.

KP7 - Ensure activities adhere to the timetable.

KP8 - Ensure dissemination results are sustainable.

KP9 - Verify that the training reaches the targeted number of participants and that participant satisfaction is at least 90%.

KP10 - Ensure participants adapt to the identified skill set with a success rate of over 90%.

KP11 - Ensure diversity in prepared scenarios and cases.

KP12 - Ensure trainer compliance rate is 95%.

This section provides details of the activities to be carried out within the scope of WP1. This section gives you the lowdown on what we'll be doing in WP1. The coordinator institution will keep an eye on the quality strategy to make sure the project stays on track and hits its targets.

TPMs and online meetings will prevent possible risks in project processes. Three/four participants from each institution will attend TPM meetings. During TPM in Türkiye (in person), the timetable will be reviewed with partners and updates will be made if necessary. The quality criteria will be mentioned in TPMs.

A practical guide for effective collaboration (PGEC) which includes all the info you need about the project work packages, the consortium structure, the project collaboration team contact details, the project activity implementation plan, the details of the work packages and the responsibilities of the partners shared with the project partners at the first TPM.

The Project Management Committee (PMC) including one representative from each partner organization, will be established at the first TPM to monitor the quality of the results and carry out evaluations of the project activities.

  • The coordinator will chair the institutional committee and carry out the secretariat processes.
  • PMC will meet every 3 months via online meetings.
  • In these meetings, committee members will discuss the progress of the work packages, the status of ongoing activities, the status of national dissemination activities, and other issues related to the project, and will reach a consensus on the functioning of all processes of the project, activities, current and/or potential problems.
  • In these meeting, the 3-month reports sent by the partners will be discussed, corrective measures will be taken and the meeting report will be shared with the partners.
  • PMC will report any problems it detects to project partners so that corrective measures can be taken.
  • Every 3 months, internal progress reports will be requested from partners.

BUDGET CONTROL

-Partners will use the project budget cost-effectively to organize a high-quality event to disseminate the project and increase the visibility of the Erasmus+ Program and EU.

-Antalya Training and Research Hospital will be responsible for the budget.

-Each activity will be examined in detail to maintain the overall coordination and ensure its completion on time and in accordance with the budget. Also, Antalya Training and Research Hospital has a key person whose role is to monitor the financial operations of the project.

-PMC will control the project's budget and time management throughout the project. Hosting partners will use their technical personal resources and their own devices during the events. This will be co-financing.

To ensure budget control;

1) The coordinator will adopt a problem-avoidance approach by outlining the available budget grant in a clear bilateral agreement that must be approved by the partner organisations.

2) This agreement will refer to the relevant Erasmus+ regulations which all partners must strictly comply with and will specify for how long a certain percentage of available funds must be used. This bilateral agreement will also determine the frequency of progress reports that must be submitted to the coordinator, as well as the documents required.

3) The first down payment will be made after the project grant payment is made by the National Agency and the bilateral contract protocol is signed. The next payment will be made after the progress report is approved.

4) All expenditures related to the project budget will be monitored through the standard template created by the coordinator institution.

5) In order to control possible budget problems, it will be stated that no further fund transfer will be provided to a specific partner organization if the funding levels determined in this bilateral agreement are not used or if it is assessed that the funds will not be used within the scope of Erasmus+ arrangements.

Within the framework of bilateral agreements, partners will be paid 40% after the contract signature, 40% after the interim report, and 20% after approval of the final report.

6) During the online kick-off meeting, the project coordinator will clearly state eligible and ineligible costs as well as relevant Erasmus+ regulations.

7) If a budget problem is identified in the submitted progress reports, the coordinator will request correction, and if the partner does not correct it, the Partner will be notified again in writing by registered mail within 2 weeks to take corrective action. If no corrective action is taken, the Coordinator will contact the National Agency for advice.

Time management

-The partners will review the project timetable, which will be used to monitor progress and edit and finalize if necessary.

-Project managers will adopt a preventive approach such as informing partners about planned activities and outputs, reminders, road maps before the determined date.

-Corrective action will be requested when progress on the planned activity is deemed not to be according to plan.

To address the risks, the following will be agreed upon by all partners

-The rights and obligations of each partner will be clearly stated in the agreement that each partner will sign with the applicant.

-The agreement will list formal procedures for handling conflicts, including online meetings and direct visits from the coordinator to the relevant partner.

-Partners will share a document on risk analysis during the first TPM. The document will describe the main risks and preventive measures.

Risk Management Plan

The risk management plan will address the risks associated with project implementation.

Risk 1: Insufficient partnership consensus: This could potentially lead to reduced interest of partners and hence slower than expected progress of the objectives of the project. Mitigation: the risk will be mitigated to ensure that sufficient broad participation in the respective researchers available, ranging from researchers, and WG leaders.

Risk 2: Insufficient participants per WG or in project activities: This could potentially lead to a lack of motivation among project researchers. Mitigation: In the development of the project the coordinator organization will organize online sessions with partner organizations.

Risk 3: Inappropriate expenses in the budget: This could potentially lead to missing expenses within the project budget. Mitigation: All details will be clarified and details by the Project Coordinator Organization in the kick-off meeting and the budget will be monitored regularly throughout the project.

Risk 4: Possible conflict between partner organizations: There's a potential for disagreement or clash of interests between the partner organizations involved in the project, leading to delays, disruptions, or breakdown of collaboration. Mitigation: To address this risk, we will establish clear lines of communication and expectations between all partner organizations from the outset. Regular meetings will be held to discuss any emerging issues and ensure alignment of goals. Additionally, a detailed conflict resolution process will be defined and agreed upon by all parties involved, allowing for swift resolution of conflicts should they arise. Finally, we will be fostering a collaborative and transparent environment that can help mitigate tensions and promote a cooperative spirit among partner organizations.

Risk 5: Insufficient knowledge exchange in and between project researchers. Mitigation: The researchers will be motivated by the project coordinator.